Cehegín Mayor Jose Soria, has announced that, following the inability of UICESA PLOD continue with the construction of the parking lot of the future audience, it has transferred the rights of the work the company Acciona Infraestructuras SA.
Soria explained at length the states through which this work has passed since its inception.
The highest representative of the council reported that the company began to suffer from undue stoppages September 2009, resulting in the possibility that Ploder enter into an arrangement with creditors (moratorium old).
"Our first goal was not to stay any creditor company or outside ceheginera without pay, and we began to receive letters from them saying they were having difficulty getting the money," said the mayor.
From that moment, and with the specter of bankruptcy hovering, the company continued to ensure that the work would end, but the City Council, after a long process of counseling, it was required to relinquish the work and give way to another company, a fact that has occurred this March.
According to Soria said, "all of the work suppliers have claimed.
Knowledge that we have here should not be anything to anyone, as the company in November settled part of the debts and we, the City Council in March, through endorsements against outstanding certificates to the company Ploder, we have same with the remaining companies, paying the remaining € 495,565. "
Now, the new company, Acciona, is making arrangements to resume the work of the future parking Cehegín Auditorium.
According to this, "is likely to start work next week."
Source: Ayuntamiento de Cehegín